Good afternoon students, colleagues and community. Below is a series of photos tracking construction progress on the Muskegon Community College Science Center. As of today, the building is mostly enclosed, red brick/exterior finishings are being added, and electrical/mechanical systems are being installed. We are still very much on track for a Fall 2015 opening. More photos will be added along the way. You may see more, including a construction webcam, at www.muskegoncc.edu/build.
October 19, 2014 – Initial clearing of property
October 30, 2014 – Grading and leveling of property, foundation laid
November 22, 2014 – Walls installed
December 8, 2014
December 22, 2014 – Crane placing roof beams
January 26, 2015
January 27, 2015 – Partial enclosure of building
February 4, 2015 – roofing and walls near completion, temporary heating system in place
Feb 23, 2015 Life Sciences Department Faculty and Staff Tour: In a new laboratory Space
Feb 23, 2015 Life Sciences Department Faculty and Staff Tour: In building atrium
Feb 27, 2015 Student Services Division Tour: In building atrium
March 4, 2015 – Building completely enclosed, exterior brick in place, prep for cement floor base
March 6, 2015 – Cement floor prep
March 6, 2015 – Cement floor poured